The Grove: construction site update

JANUARY 2021

Progress report:

80% of Sewage drainage Pipelines and Manholes – Achieved

80% of Water drainage Pipelines and Manholes – Achieved

80% construction of water hydrants – Achieved

100% Road Excavation- Completed

90% Rock Blasts and Moved to various plots for Structural integration – Achieved

60% of Laterite filling and road construction for all roads; Road 1 -11 – Achieved

June 2020

September 2020